Exterior Consulting Innovation, Inc. (ECI)

SEALY PROFILE

                     
EXTERIOR HISTORIC RESTORATION
THE UNIVERSITY OF TEXAS OPEN GATES
CONFERENCE HALL "SEALY MANSION"

FACILITY CONSTRUCTION
   - Structure: Three (3) story structure with load bearing masonry and stone walls over a full basement.
   - Wall System: Cut limestone foundation and base, hand pressed brick, load bearing walls with terra
     cotta trim. The fenestration in the structure is wood sash.
     Roof System: Wood trusses, wood rafters, wood decking and clay tile with sheet copper flashings
.

CONSULTING SERVICES PROVIDED:

   - Evaluation and Assessment: Provided a report, restoration program, schedule and budgets.
   - Design: for historical restoration of exterior conditions.
   - Construction documents: specifications, plans, elevations and details were developed for the exterior and merged with structural      and interior demolition documents to form the Bid package.
   - Meetings: submittal recommendations, project inspection, review payment requests, final inspection, review project close-out      documents.
     Quality Assurance Inspection: Review and documentation of work in progress.


SOLUTIONS:

   · Stone patching, stone consolidation. Stone patching, masonry restoration and cladding repairs.· Correction and repairs to wall      deficiencies.· Waterproofing at horizontal exterior patio area.· Terra cotta repairs and replacement.· Refurbishment of wood      windows to prevent water infiltration. · Building cleaning and sealing.· Replacement of exterior building sealants.below grade      waterproofing repairs.· Foundation drainage and waterproofing at building perimeter.· Roofing Repairs

PROJECT START:
   Estimated Cost: $400,000.00 Actual Cost: $380,000.00
   Start: As Scheduled Completed: On Schedule

KEY PERSONNEL: Michael C. Tolson
   · Factors that determined the selection of roof and wall repair systems:
   · Cost and completion schedule.· Appearance and life of materials.· Anticipated facility usage.· Ease of repair. · Long term      maintenance.· Concern for preserving and restoring the appearance.· Concern for preserving and restoring the appearance of this      historical structure.

· Construction Cost: $380,000 Estimated Cost: $400,000